economic

Zawia Power Station's Third Unit Returns to National Grid After Delayed GE Vernova Maintenance

|Libya Conflict

The General Electricity Company of Libya (GECOL) reconnected the third unit of the Zawia Combined-Cycle Power Station to the national grid on September 4, 2026, restoring 150 MW of capacity after US firm GE Vernova completed a long-delayed overhaul. The maintenance, originally due to finish July 6, 2026, was repeatedly interrupted: GE Vernova evacuated engineers for nine days in May 2026 amid militia clashes near the plant, and again in August 2026 after a drone attack forced an emergency evacuation; GE Vernova also acknowledged technical difficulties contributed to the delay. The restored capacity offers modest relief for western Libya's grid after a summer of prolonged blackouts that fueled nationwide civil-disobedience protests.

Zawia Combined-Cycle Power Station's third unit reconnects to Libya's national grid, Sep 4, 2026
Zawia Combined-Cycle Power Station's third unit reconnects to Libya's national grid, Sep 4, 2026 — Libya Herald